>> Home >> Communication >> History of the port >> Birth of a modern port
Histoire du port
Birth of a modern port :
In 1862, the Chamber of Commerce of Calais began to take an interest in the major projects underway at the port, especially the construction of a wet dock and a scouring basin west of Calais. In 1874, the projects were subjected to a public benefit inquiry, and after having passed the first two preliminary stages, the Chamber received provisional approval to downgrade the East Face. Lastly, on December 14, 1875, on the proposal of the Minister for Public Works, a law officially declared the public utility of the project, which consisted of :

  • Creation of a holding basin,
  • New outer harbour intended for passenger liners,
  • Vast basin in the east connected to the outer harbour by two locks,
  • Relocation of the Calais Marine Terminal from Bassin du Petit Paradis to a new area between the towns of Calais and Saint-Pierre,
  • Development of the Calais canal.


Work began when the law of April 29, 1879 ordered the retirement of the old north, east, and south faces and the construction of the new enclosure. This law paved the way for expansion of the quayages, the construction of a dry dock, and the substitution of a large shipping passageway with a canal lock bypass. These improvements and others such as the widening of the canal, the construction of new quays in the outer harbour, the doubling of the wet dock lock, and the deepening of the tidal basin lock were included in the amended law of July 28, 1879.

The first stone of the wet dock was laid by the Minister of Public Works, Varoy, accompanied by the president of the Senate, Leon Say, who paid a visit on July 19, 1880 in order to visit work of the port and the test pit of the underwater tunnel in Sangatte. In this same year, a study was conducted on the organisation of equipment at the quays of the new port. Finally, on September 22, 1983 the Chamber of Commerce obtained the concession. The equipment and facilities included :
  • Shelters along the quayages to protect goods,
  • Hydraulic cranes,
  • Hangars spread over the south-west section of the outer harbour. These tools were supplemented by a vast railway network.
In 1889, the Chamber of Commerce requested the study of a project to build a bridge-dam in the outer harbour to the west of the tidal dam. The cofferdam which separated the channel from the outer harbour was burst at the end of February 1889 and water penetrated for the first time in the new basins the night of February 27th, 1889. The new port was inaugurated on June 5, 1889 by French President Sadi Carnot. A commemorative medal was struck. In order to increase publicity, the Chamber published a booklet entitled "The Port of Calais inaugurated by Mr Carnot, President of the French Republic, June 3, 1889". On November 4, 1889, it was decided to name the new wet dock after Carnot. In recognition of the eminent members of the Chamber who had worked for the new port, the south-west quay of the outer harbour was named after Paul Dévot, and the west quays of the Carnot Basin were baptised 'Crespin' and 'Baker'. The Chamber requested the authorisation to give the same names to the hangars and suggested naming the swing bridges 'Vétillard'.

The new Port of Calais benefited, especially initially, from the passenger traffic to and from England. Thanks to its diverse facilities, the Port of Calais could accommodate increasingly large, faster, and more comfortable boats able to carry out Cross-Channel services with fixed times. Once inaugurated, the Port of Calais was still in need of improvement. Construction of the tidal quay began in 1890, and the new pier was completed in 1896.



By the decree of January 26, 1895, the Prefect of Pas-de-Calais prescribed a public benefit inquiry into the draft project for improving the western part of the port, which included following work :

  • Rebuilding the wet dock lock,
  • Dredging of a channel in the dry harbour and wet dock and underpinning of the riprap and wharves of the basin,
  • Replacement of the riprap of the Baleine by a wooden landing stage and a masonry pierhead,
  • Repair of the citadel bridge,
  • Reconstruction of the long bridge extending the existing lock with a carriage road.
The Chamber of Commerce had reserves with regards to the project proposal, particularly about the length of the long bridge, which it considered much too narrow. In addition, the commission report was unfavourable, and as a result the file was handed over to the engineering corps to be re-analysed. On April 7, 1898, the Chamber successfully pleaded its case and construction was authorised of a new 17-metre wide lock in the port. Work was completed in 1906.

The Law of February 24, 1906 declared of public utility the second stage of the west port improvement project :

  • The removal of Fasquel quay and the flushing basin,
  • Construction of a wide masonry dam across the flushing basin, an extension of the large dike in masonry which connected the latter to the coastal road,
  • Construction of a breakwater and landing stages where the flushing sluice was located,
  • Various other improvement projects : reconstruction of the western pier, improvement of the channel, etc.
In 1912, the Chamber of Commerce began to consider a project that would convert the East flushing basin into a large inner harbour with quays and docks. On October 13, 1916, it deliberated on another East flushing basin conversion project, this time for the transformation of the flushing basin into a wet dock with a 25-metre wide chamber lock.

From 1916 to 1925, various development projects for the East were presented and approved by the Public Authorities. Amongst other things, in 1919 the chamber recommended the creation of a port-canal extending from Calais towards Dunkirk in the Flanders alluvial plain.

In 1924, a ministerial decision stipulated that from that point forward all Port of Calais expansion projects should be directed towards the East.

The decisions of July 19, 1928, of September 23, 1929, May 22, 1930, July 26, 1935, and July 1, 1946 prescribed studies for developing the East port, but none were met with any success. The users of the port, frustrated by this standstill, came to an agreement with the Chamber of Commerce to back the State in reconstructing certain elements of the port and to redirect development projects towards the West.

Unfortunately, the Second World War devastated port activity and in 1945 the port was almost entirely destroyed and required complete reconstruction. The formidable task was undertaken of making the port accessible to the goods and passenger ships as quickly as possible.

Paul Devot quay in 1944

Vétillard lock at the Liberation

Shipping basin and Carnot basin at the Liberation

After the English army handed the port over to French authorities in 1946, work began immediately on the maritime station platform to restore sea and rail connections with England. Next came the reconstruction of the quays of the outer harbour and Carnot Basin, which had been mined by the Germans. Lastly, work began on the West Basin, which had been partly filled, and since 1950 the port has almost been at its pre-war capacity. Cranes and gantries which the Germans had disassembled were recovered in Germany, Austria and Bulgaria, with the addition of English and American cranes paid for by the Marshall plan, the port was very quickly re-equipped. However, the war had profoundly changed shipbuilding, leading to the appearance of increasingly large and specialised ships such as tankers, ore tankers, oil tankers, bulk carriers, Ro-Ro ships, container ships, etc., which required the ports to acquire new equipment for receiving and handling goods. The Paul Devôt quay was refitted to receive ships of 15-20,000-tonne ships and the Carnot Basin was develop to receive Ro-Ro ships.

It was not until the 1970's that the Chamber managed to bring the East port project back to the table. Indeed, much had happened in the meantime :

  • Revenue from the Cross-Channel port made such a project feasible.
  • The establishment of new companies such as Tioxide and Union Carbide in the Dunes zone, was made possible by the port configuration.
The project studied in the 70's would have enabled the berthing of ships weighing approximately 40,000 deadweight tonnes, which corresponds to a draught of 12.5 m.
When Mr Henri Ravisse became president of the CCI in 1980, all the files were ready but the regulatory authorities would not embrace the project wholeheartedly because of protest from Calais inhabitants. This was also the period that the new Channel tunnel project was gaining momentum. President Ravisse decided that it was time to make his voice heard, to inform others about the importance of the economic benefits that the port brings to the Calais economy and the necessity of securing port activity, beyond the creation of a hypothetical fixed link. It was difficult to convince stakeholders of the importance of a concrete, prudent plan for the future of an average French port when compared with the abstract, futuristic connotations of the fixed link. Thanks to his tenacity, President Ravisse was able to make headway. The list of projects completed during his mandate is impressive :

  • Completion of the new Cross-Channel terminal (1980),
  • Relocation of the East pier (1984),
  • Expansion of the Cross-Channel terminal (1987),
  • Doubling of berths 3 and 4 (1979-1980),
  • East port,
  • Connection to the East bypass,
  • East port cranes,
  • Le Calaisien tug boat,
  • Berth VI (1987),
  • Berth VII (1990),
  • Berth VIII (1995),
  • Rebuilding of berth V (1996),
  • Ro-Ro berth for new cars (1992),
  • Catamaran berth in the East port (1991),
  • Refitting of berth 2 for catamarans,
  • Reorganisation of the Cross-Channel terminal,
  • Construction of grade-separated roadways at the terminal
Haut de page